Generate burndown chart for a swimlane

180 Views Asked by At

I have added 2 swimlanes to manage 2 projects. However, when I generate the Burndown chart it displays the performance of both projects. How can I display a burndown chart for a particular swimlane ?

Note: I am not allowed to add any pluging

1

There are 1 best solutions below

0
On BEST ANSWER

The Burndown Chart report on Jira's sprint board tracks the progress of all issues in sprint. To view two separate reports you have to create two separate scopes (one per project) and add them to two different sprints. You can run parallel sprints in Jira, just make sure that the Parallel Sprints checkbox is checked in Jira configuration.