How to perform the calculation details for field ETC(Cost) in Clarity PPM?

524 Views Asked by At

One of our report needs the calculation of ETC(Cost) at task level. While checking I get the general formula:

ETC (Cost): Cost of Estimate to Complete
ETC (Cost) = remaining labor cost (ETC * billing rate) + remaining non-labor cost

But I am not able find any matched database columns (it is a virtual attribute in Clarity). Expecting the table details where I can query the field.

1

There are 1 best solutions below

0
On BEST ANSWER

Virtual attributes at "Clarity/CA PPM" are "real time" calculated so you will not find the data in a field of task tables.

However, there is a database view where you can find the SQL formula used and even the result(be aware that using data from views is not a best practice)

Check views: ODF_TASK_V and ODF_TASK_V2