Set baseline programmatically in ProjectServer

416 Views Asked by At

How I can set the baseline programmatic-ally in Microsoft project server?
Are there any blogs about this?

1

There are 1 best solutions below

0
Klaus Kuplen On BEST ANSWER

I am not sure in what context you are working. If you are in VSTO, try this: Application.BaselineSave

As far as I know PSI does not offer a method to set a baseline What PSI does and does not