I am learning Project Server 2010 these days and want to know if I had to upgrade from an existing Project Server 2007 to 2010 version, how many days can it take?
Isn't it a day or at max 2 days job considering the following:
- Current Project Server 2007 consists of one server farm with one SQL Server machine and one Project Server machine
- No 3rd party web parts installation or customization has been made
Or it can take longer than that?
http://blogs.msdn.com/b/chrisfie/archive/2010/05/27/how-to-upgrade-from-project-server-2007-to-project-server-2010-in-10min.aspx
I have had similar experiences. If you don't have any 3rd party apps or customizations, it is a breeze.