Can I, somehow, based on time stamp and how much is done, estimate time and date for when a job is complete? I got this log that a bot I've made writes in column A time [yyy-mm-dd hh:mm], and in column B it wrights how much is done. It sorts it all with newest on top.
Estimating when it's done in excel
100 Views Asked by Sodori At
2
There are 2 best solutions below
5

Consider:
In this example the time span is 1 hour and the percent complete in the time span is 78%
Cell C1 contains:
=100-B1
the percent remaining to be done.
In cell D1 is the formula:
=(A1-A2)/B1
D1 yields the time required to complete 1%
Finally in E1:
=D1*C1
the time required to complete the work!
(Note...C1,D1,E1 can be combined into a single formula)
EDIT#1
The formats of E1 and D1 were picked to display the relevent parts of the data
The format of D1,E1 is: mm-dd hh:mm:ss.00
Change this format to suit your needs!
Gary's answer is correct, but for convenience if the 2nd row of data can be an arbitrary progress status (not just start of task = implicitly 0%), and if you use percentage number format (or decimals) and you would like to get the end date instead of just the duration, use following formula: